Refurbishment of the natural draft cooling tower in Voerde

Performed services – building time of 6 weeks in 2 shifts

  • building of the cooling packages with the glue method
  • building of the drip catchers by interlocking them
  • disassembly of the entire drip catching layer
  • loading and transport of asbestos cement waste
  • planking of the 8.000 sm drip catching layer
  • sealing of the drip catching layer with PE-foil including the protection
  • removal of 1/4 of the cooling packages
  • removal of the winter-ring-pipeline including the coverage
  • mounting of the cooling packages
  • mounting of the winter-ring-pipeline
  • disassembly of the planked area
  • laying out of the new drip catching packages