New construction of a 16 part cell cooling tower Hamm – Uentrop

Performed services – building time of 7 months

  • buidling of cooling packages with the glue method
  • building of the drip catching layer by interconnection
  • ground level pre-assembly of the single supporting elements of GFK
  • positioning of the supporting elements with a mobile crane
  • completion of the GFK construction
  • installation of the cooling packages, the water distribution and the drip catching layer
  • mounting of the acoustic backdrops
  • mounting of the fans and polygones incl. alignment
  • mounting of the facades and staircase towers
  • mounting of the railings